1 / 22

[Front]


Describe Planned Value
[Back]


The original estimated work planned that should have been completed as of today.

Practice Known Questions

Stay up to date with your due questions

Complete 5 questions to enable practice

Exams

Exam: Test your skills

Test your skills in exam mode

Learn New Questions

Dynamic Modes

SmartIntelligent mix of all modes
CustomUse settings to weight dynamic modes

Manual Mode [BETA]

Select your own question and answer types
Specific modes

Learn with flashcards
Complete the sentence
Listening & SpellingSpelling: Type what you hear
multiple choiceMultiple choice mode
SpeakingAnswer with voice
Speaking & ListeningPractice pronunciation
TypingTyping only mode

Project Management - T1 - Leaderboard

1 user has completed this course

No users have played this course yet, be the first


Project Management - T1 - Details

Levels:

Questions:

22 questions
🇬🇧🇬🇧
Describe Planned Value
The original estimated work planned that should have been completed as of today.
Describe Earned Value
The original estimated planned value of work actually accomplished
Describe Actual Cost
Actual cost incurred for the work completed, as of today.
Describe Budget at Completion
Planned budget for the total project
CV = ?
EV-AC
SV = ?
EV-PV
SPI = ?
EV/PV
EAC = ?
BAC/CPI
ETC = ?
EAC-AC
VAC = ?
BAC-EAC
PCIB = ?
EV/BAC
PCIC = ?
AC/EAC
CPI = ?
EV/AC