Question:
A schedule compression method that changes the relationship of activities. With fast tracking, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. Fast tracking can be accomplished by changing the relation of activities from FS to SS or even FF or by adding lead time to downstream activities. However, fast tracking does add risk to the project.
Author: Mitch PalmerAnswer:
Fast tracking
0 / 5 Â (0 ratings)
1 answer(s) in total