Scrum Teams create six artifacts: Product Backlog, Sprint Backlog, Increment, Product Goal, Sprint Goal, Definition of Done. a) True b) False
Author: Avinash UpadhyayAnswer:
B) False In Scrum, only the following three are called artifacts: Product Backlog, Sprint Backlog, and Increment. Other three (Product Goal, Sprint Goal, and Definition of Done) are reflections of the ‘commitment’ to these artifacts. Correct answer is ‘b.’