Question:
In the Sprint Review, the presentation of the product Increment to stakeholders is a) To get the Sprint completion sign-off. b) To provide the status of the project. c) To elicit feedback.
Author: Avinash UpadhyayAnswer:
C) To elicit feedback. The Sprint Review is an informal meeting, not a status meeting, and the presentation of the Increment is intended to elicit feedback and foster collaboration. Correct answer is ‘c.’