SCRUM REAL QUIZ

» Start this Course
(Practice similar questions for free)
Question:

Which of the Following statements is true? Select all that apply a) After Sprint planning, a sprint cannot proceed without complete requirement specification. b) After Sprint planning the Sprint cannot proceed without Sprint Goal. c) After Sprint planning the Sprint can proceed without a complete sprint backlog. d) After Sprint planning, a sprint cannot proceed without complete Architecture.

Author: Avinash Upadhyay



Answer:

B) After Sprint planning the Sprint cannot proceed without Sprint Goal. c) After Sprint planning the Sprint can proceed without a complete sprint backlog.