Question:

A product owner is also knowledgeable on technology. In addition to product requirements, they also impose some technical conditions that the product should meet. These conditions must be added to the a) Product backlog b) Sprint Backlog c) Definition of Done

Author: Avinash Upadhyay



Answer:

C) Definition of Done Every Product backlog item should be about product's needs to bring business value. The Conditions that the Product owner brings here is about the technical constraints.So, it should be added to Definition of Done