Question:
An inspector finds a work aspect deviate outside acceptable limits, and that the resulting product will be unacceptable. When will the team adjust this work aspect to minimize the deviation? a) In the next Scrum event. b) As soon as possible. c) After the Scrum master approves the Adjustment
Author: Avinash UpadhyayAnswer:
B) As soon as possible.