Question:

How would you typically calculate the production budget?

Author: Hjalmer Pedersen



Answer:

Budgeted sales + target closing finished goods stock - opening finished goods stock = Units to be produced


0 / 5  (0 ratings)


Budgeted sales + target closing finished goods stock - opening finished goods stock = Units to be produced