Question:

Construction Contracts: (company doing the building for another company) % Profit Earned Equation

Author: LandiniLizard



Answer:

(Cost Incurred / Total Expected Cost) = % Complete Contract Price - Total Expected Cost = Profit Profit x % = Profit Earned