The Product development Project is about delivering an internal feature for an organization. The team has good skill composition and worked on similar projects. The Sprint length can be a) Decided after First release b) Ignored since it is an internal project. c) A maximum of one calendar month

Author: Avinash Upadhyay



Answer:

C) A maximum of one calendar month